top of page
PROJECT INFORMATION
Client:
AP TRANSCO
We constructed a new power station in Pampanurthanda (Bhanukota Village) and installed a double circuit power line from Hindupur to Pampanurthanda (Nuthimadugu) in Anantapur District. This helped improve electricity supply in the area.
200KV/132 KV substation at Bhanukota and 220KV Line from Hindupur to Bhanukota, Anathapur, Andhra Pradesh
PROJECT INFORMATION
Bhanukota, Andhra Pradesh
Some Interesting Facts
Project Cost
109 Cr
Project Status
Completed
74 Kms
Length
PROJECT GALLERY
Other Projects
bottom of page