We constructed a new power station in Pampanurthanda (Bhanukota Village) and installed a double circuit power line from Hindupur to Pampanurthanda (Nuthimadugu) in Anantapur District. This helped improve electricity supply in the area.

200KV/132 KV substation at Bhanukota and 220KV Line from Hindupur to Bhanukota, Anathapur, Andhra Pradesh

परियोजना जानकारी

Bhanukota, Andhra Pradesh

Bg for Testimonial.png

कुछ रोचक तथ्य

परियोजना लागत

109 Cr

परियोजना स्थिति

Completed
74 Kms

लंबाई